Construction Progress

Best viewed on Firefox to see all the images.

----------------------------------------------------------------------------------------------------------------------------------------------------

If you are a Citylife Client who has purchased in any of our projects, you may keep up to date with construction of your project here.

Please keep checking back on this page for updates. 

IF YOUR PROJECT BELOW IS SHOWING AS AROUND 4 MONTHS OR LESS TO COMPLETION, YOU SHOULD ALSO NOW VISIT OUR SECTION CALLED "SETTLEMENT PROCESS"

ILK SOUTH YARRA:

PROJECT FULLY SOLD OUT, EXCLUDING A COUPLE OF PENTHOUSES.

. FULL COMPLETION ESTIMATED MID 2013.

DEMOLITION OF EXISITING BUILDINGS STARTED, MARCH 2011.

 CONSTRUCTION PHOTOS AS AT MAY 2011:

.

CONSTRUCTION UPDATE - NOVEMBER, 2011

Following months of hard work, the demolition of the former ANZ building fronting Toorak Road is now complete.

They have excavated basement 2 and foundations are now 80 per cent complete.

The ground conditions have been good and it is their expectation that over the coming month, inground services will be installed and the commencement of the first car park level - B2, will start being poured.

During the excavation to the bottom of the excavated car park area, there has been a fever of activity with excavators and trucks removing soil destined for landfill. Demolition of the existing structure has been a noisy and difficult process.

The first tower crane to the eastern end of the site will be erected in the coming weeks.


----------------------------------------------------------------------------------------------------------------------------------------------------

HI DOCKLANDS: PROJECT FULLY SOLD OUT

Up & Away! The $180M HarbourOne Tower  FINISHED!


MAB awarded the construction tender to Brookfield Multiplex, a
world renowned builder with over 40 years' experience constructing
some of Melbourne's most admired apartment towers.


UPDATE NOVEMBER 2011:

Construction COMPLETED.

Up to level 17 :  SETTLEMENTS  NOVEMBER

Level 18 to level 22 : SETTLEMENTS NOW NOVEMBER/DECEMBER 2011.


---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

THE ALBERT TOWER. 

Planning permits issued early 2011 

CONSTRUCTION STARTED SEPTEMBER 2011

CONSTRUCTION UPDATE NOVMBER 2011:


Demolition of the exisiting building a completed.  Updated photos here:

http://www.flickr.com/photos/perriprojects/sets/72157627935098882/with/6323998367/

Construction snapshot:


  Demolition, site establishment and foundation works
 Early 2012: Main structure to start to come out of the ground
 September 2013: Expected completion

Albert in the PRESS:

PRESS ONE

PRESS TWO

BUILDER APPOINTED: Icon Construction

Icon is one of Melbourne’s top performing development and construction companies and prides itself on delivering high quality projects on schedule by employing and supporting motivated, flexible and focused teams. Icon was founded in 1997 by Ashley Murdoch, Nicholas Brown and Lou Raunik and now turns over in excess of $150 million dollars a year and employs around 85 people.

Icon has delivered many high-profile Melbourne residential developments including A’Beckett Tower (Melbourne CBD), Harper Lane (St Kilda), NewQuay West (Docklands), 534 Bridge Road (Richmond) and 28 Beaconsfield Parade (Port Melbourne). Projects currently underway include lilli (South Yarra), 50 Claremont (South Yarra) and A Place To Live (Richmond).



settlement process                                                                                                        new projects                                                                                                                contact us